Anantam IASPost · 17 April 2026

PPP in Healthcare and Swiss Challenge Method (UPSC Economy)

Study Notes · General Studies · GS III · Health · Indian Economy

Public-Private Partnerships in healthcare, Swiss Challenge method for PPP awards, National Monetisation Pipeline updates and UPSC GS-III analysis.

Two reform levers come together in this guide: Public-Private Partnerships (PPP) in healthcare, which COVID-19 made unavoidable, and the Swiss Challenge Method, a procurement approach increasingly used to award PPP projects including the National Monetisation Pipeline (NMP). Both sit inside GS-III debates on infrastructure, governance and public service delivery.

Part 1: PPP in Healthcare

Background

COVID-19 exposed deep flaws in India's healthcare system — shortages of beds, ICU capacity, oxygen, trained personnel and diagnostics. Public health spending remains around 2% of GDP against a National Health Policy 2017 target of 2.5%. Out-of-pocket expenditure is around 47-50% of total health expenditure, pushing millions into poverty every year.

The UN SDG-17 highlights partnerships as a cross-cutting goal. PPP in healthcare can help deliver the 4 As — Accessibility, Affordability, Availability and Awareness — provided contracts protect poor patients and maintain public oversight.

How PPP Can Transform Indian Healthcare

Improving efficiency of hospital management: Management of select public hospitals can be contracted to private partners for upgradation, with the interest of the poor protected through government reimbursement. Benefits include expanded capacity, lower government burden and access to private-sector expertise and equipment.

Addressing shortage of medical personnel: Set up new medical colleges in PPP mode linked to existing district hospitals. The NITI Aayog‘s 2019 proposal for linking district hospitals to private medical colleges was controversial but is being rolled out in select states.

Reducing out-of-pocket expenditure: Enable poor patients to access private hospitals with costs reimbursed by government insurance — the Ayushman Bharat PMJAY model, now covering 12+ crore families with Rs 5 lakh annual cover.

Accessibility and affordability at primary level: Contract out Primary Health Centre (PHC) management in remote areas. PPP with private labs for 24×7 diagnostic testing under PM-JAY Diagnostic Scheme.

Affordable medicines: Expansion of Pradhan Mantri Bhartiya Janaushadhi Pariyojana (PMBJP) — over 14,000 stores operational by 2025; average 50-90% cheaper than branded equivalents.

IT infrastructure: PPP investment in universal health records and telemedicine — the Ayushman Bharat Digital Mission (ABDM) and eSanjeevani platform. Srinath Reddy Committee (High Level Expert Group on UHC, 2011) recommended UHC framework enabled by IT investment.

Preventive care: Engage NGOs and private providers for community health worker training and information dissemination, strengthening ASHA/Anganwadi networks.

Risks and Caveats

Cross-country experience — the UK's NHS partnerships, Germany's sickness fund model, Thailand's UHC — shows PPP works when regulation is robust, pricing is transparent and public financing is predictable.

Part 2: Swiss Challenge Method

What It Is

The Swiss Challenge Method (SCM) is a procurement process used for awarding PPP projects based on unsolicited proposals. The sequence:

  1. An interested private party submits an unsolicited project proposal to the government.
  2. If the government finds it viable, it publishes the proposal and invites competing bids.
  3. The original proponent is given the right to match the best competing bid.
  4. If the original proponent matches or beats, it wins; otherwise the best bid wins.

Projects That Used SCM

SCM also supports the National Monetisation Pipeline (NMP) — Rs 6 lakh crore asset monetisation over FY22-25 targets — by bringing in innovative private proposals for brownfield assets.

Benefits

Challenges

NITI Aayog has flagged the need for a National Policy Framework for SCM to standardise criteria, timelines and transparency norms.

Comparison with Other PPP Models

ModelDescriptionExample
BOT (Build-Operate-Transfer)Private builds, operates, transfers after concessionMany NHAI highways
BOOTBuild, Own, Operate, TransferPower projects
HAM (Hybrid Annuity Model)40% government, 60% private; annuity paymentsNewer highway awards
TOT (Toll-Operate-Transfer)Brownfield asset leased to privateNHAI monetisation
Swiss ChallengeUnsolicited proposal with right to matchStation redevelopment

Latest Developments (2024-26)

UPSC Relevance

GS-III Mapping

GS-II Mapping

Prelims Bullets

Mains Angles